Step 1: Order acceptance and parts confirmation

We pick, inspect and clean the parts as ordered. The build team receives the order and parts and assembles the clubs by hand.

Step 2: Shaft Machining

The shaft, which is pre-made to a length, is then cut to the specifications determined during the fitting.

Step 3: Hammering in the ferrule

Drive the ferrule into the shaft to the specified depth.

Step 4: Swing weight and length measurement

We use the same swing weight measuring machine used by our fitters to adjust the balance to your specifications and ensure the club length is exactly as you ordered.

Step 5: Adhesion

Using a two-part adhesive, the head is glued so that the logo on the shaft matches the club face.

Step 6: Torque Inspection

The strength of the glued clubs is inspected.

Step 7: Loft and lie angle adjustment

We will adjust the loft and lie angle according to your order.

Step 8: Shaving the ferrule

Shave the ferrule so that the seam between the ferrule and the head is flat.

Step 9: Grip Insertion

Insert the grip so that the logo on the grip matches the club face.

Step 10: Final swing weight measurement & cleaning

We check the swing weight again using a measuring device to confirm the finish. Once all steps are completed, we check the order form one last time to make sure the club is assembled correctly and according to the order. We carefully polish and clean the club and collect the attached head cover, products, and other necessary items.

Step 11: Shipping

It will be carefully packed and shipped in a luxurious black PXG box.